Infrastructure

Answered by: 
Hon Tertuis Simmers
Question Number: 
10
Question Body: 

Question by Hon Wessels.

With regard to extortion at departmental construction sites:

(a) How many construction sites are currently the target of extortion, (b) how many of these incidents are being investigated by the police, (c) what are the names of the sites being targeted, (d) what is the value of these construction projects and (e) how are timelines being affected by this?

Answer Body: 

(10)(a) – There are 6 sites which are currently extortion targets.

 

(10)(b)(c)(d)(e) refer to table below:

 

(c) Name of Project Affected

(b) Investigated by Police? (Yes/No)

(d) Value of Project

(e) How are timelines being affected by this?

 

Driftsands Relocations Project (Site A)

Yes – SAPS Case 73/6/62024

R 21 419 200

Six weeks of project delays

Airport Infills (Luyolo, Tambo Village sites)

Yes: The case numbers are:

  • 447/02/2022
  • 268/03/2022
  • 167/10/2022
  • 180/11/2022
  • 202/11/2022

R 248 m

19 months of project delays.

Management, Maintenance and Security of TRA 5, 5.1 and 6 in Delft South

Yes 3/01/2024 (Dealt with in a cluster of Incidents perpetrated by the same group in the area)

R 12 m

No delays. Measures to Mitigate risks put in place

Valpark Primary School

Yes. SAPS assisted with securing site.

R3 737 219

Contract terminated. Phase 2 being initiated. 3 year delay.

Ravensmead CDC replacement

Not required

R105 281 028

6 months

Clarke Primary School

Yes

R386 183

Phase 2 being initiated. 3 year delay.

 

Date: 
Thursday, August 8, 2024