Education
- Whether her Department has plans to build new schools in the current year; if so, what are the relevant details;
- (a) how many schools are being restored or will be undergoing major maintenance or repair work during this year and (b) what are the names of the schools?
(a) It is unclear whether the question refers to the financial year, or the calendar year.
If referring to the 2019/20 financial year ending 31 March 2020, the following new and replacement schools are being delivered:
- Avondale Primary School (Replacement School) was completed in completed in Quarter 2 of 2019/20.
- Delft High School (New School) was completed in Quarter 1 of 2019/20.
- Philippi Secondary School (Replacement School) was completed in Quarter 3 of 2019/20.
- Qhayiya Secondary School (Replacement School) was completed in Quarter 1 of 2019/20.
- Silikamva High School (New School) was completed in Quarter 1 of 2019/20.
If referring to the 2020 calendar year:
- Blackheath Primary School (Replacement School) is anticipated to achieve contractual Completion – of the 2nd phase of construction works comprised of external works including demolition & provision of a new sports field - in Quarter 4 of the current 2019/20 financial year. The 1st phase of construction works achieved contractual Completion in Quarter 3 of the current 2019/20 financial year.
- Delft-North Primary School (New School) is anticipated to achieve contractual Completion in Quarter 1 of the next 2020/21 financial year.
- Disa Road Primary School (New School) is anticipated to achieve contractual Completion in Quarter 4 of the current 2019/20 financial year.
- Stofland Primary School (New School) is anticipated to achieve contractual Completion in Quarter 1 of the next 2020/21 financial year.
- Diaz Primary School (Replacement School) is anticipated to achieve contractual Completion – of the 2nd phase of construction works comprised of external works including demolition & provision of a new sports field - in Quarter 1 of the next 2020/21 financial year. The 1st phase of construction works achieved contractual Completion in Quarter 3 of the current 2019/20 financial year.
- Umyezo Wama Apile Primary School (Replacement School) is anticipated to achieve contractual Completion (1st phase of construction) in Quarter 3 of the next 2020/21 financial year.
- Harmony Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 1 (1st phase of construction) of the next 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 3 of the next 2020/21 financial year.
- Panorama Primary School no 2 (in Vredenburg) is anticipated to achieve contractual Completion in Quarter 2 (1st phase of construction) of the next 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 3 of the next 2020/21 financial year.
- Turfhall Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 2 (1st phase of construction) of the next 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 3 of the next 2020/21 financial year. The execution of this project is at risk due to Group Five Construction, currently in Business Rescue, not making adequate progress with on-site construction works. The continued feasibility of completing this project with Group Five is being evaluated at present.
- Kwa-Faku Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 1 (1st phase of construction) of the next 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 3 of the next 2020/21 financial year.
- Crestway High School (Replacement School) is anticipated to achieve contractual Completion – of the 2nd phase of construction works comprised of external works including demolition & provision of a new sports field - in Quarter 1 of the next 2020/21 financial year. The 1st phase of construction works achieved contractual Completion in Quarter 3 of the current 2019/20 financial year.
- PC Petersen Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 1 (1st phase of construction) of the next 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 3 of the next 2020/21 financial year.
- Willows Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 1 (1st phase of construction) of the 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 2 of the 2020/21 financial year. The execution of this project is at risk due to Group Five Construction, currently in Business Rescue, not making adequate progress with on-site construction works. The continued feasibility of completing this project with Group Five is being evaluated at present.
- Woodlands Primary School (Replacement School) is anticipated to achieve contractual Completion in Quarter 4 (1st phase of construction) of the current 2019/20 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 1 of the next 2020/21 financial year.
- Sunray PS (Replacement School) is anticipated to achieve contractual Completion in Quarter 1 (1st phase of construction) of the 2020/21 financial year. The 2nd phase is anticipated to achieve contractual Completion in Quarter 2 of the 2020/21 financial year.
(b) It is unclear which financial year is referred to.
238 Schools are currently receiving (first list of 105 below) or, are planned to received maintenance (second list of 133) in 2020
2019/20 Financial Year projects that have not yet reached completion by the end of the Third Quarter of 2019:
- Perseverance Sek
- President HS
- Rawsonville PS
- Tafelberg Lsen (roof)
- Tafelsig SS
- Tenterden Place of Safety (satellite campus of OYC)
- Die Bron PS
- Tuscany glen sec
- Aurial College
- Bishop Lavis PS
- Garlandale PS
- Goedehoop PS
- Greyton PS
- Imizamo Yethu Senior SS
- Mary Kihn Lsen
- Mokone PS
- Murraysburg HS
- Oj Erasmus Ngk PS
- Perivale PS
- Siyabulela PS
- Thornton Road PS
- Welcome PS
- Range SS
- Y2K College HS
- Cedar PS
- Northpine PS
- Noorder Paarl SS
- Andile PS
- Cascade PS
- De Villiers PS
- Bonteheuwel SS
- Saambou PS
- Fanie Theron PS
- George Fredericks PS
- Morgenson PS
- Cornflower PS
- Ceres SS
- Charleston Hill SS
- Paarl Vaardigheidskool
- Eendekuil PS
- Sibelius SS
- Cathkin SS
- Excelsior Belville PS
- Hermeslaan PS
- Hopefield PS
- Maskam PS
- Silverstream SS
- Drostdy SSKV PS
- Fraaisig PS
- Ned Doman HS
- Oscar Mpetha HS
- Bertie Barnard LS
- FJ Conradie PS
- Meulenhof PS
- Boston PS
- Dr Van Der Ross PS
- Gericke LS
- New Dawn Park PS
- Rio Grande PS
- Sonderend PS
- Middelrivier PS
- Olympia SOS
- Danie Ackermann PS
- Eluxolweni PS
- Heidelberg HS
- Central Park PS
- Chumisa PS
- Encotsheni PS
- Rosebank Junior
- Vukukhanye PS
- Helderberg PS
- Lavisrylaan PS
- Olifantsvallei PS
- Saron PS
- Sinako HS
- Vuyani PS
- Petunia PS
- Morrisdale PS
- PJB Cona PS
- Eastville PS
- Robertson Voorb
- Waveren HS
- Indwe SS
- Tyholora PS
- De Grendel LSEN
- Oasis LSEN
- Philadelphia PS
- Thomas Wildschutt Junior PS
- Vusisizwe SS
- Milkwood PS
- Voortrekker HS
- Karatara LS
- Forest Heights PS
- Harry Gwala SS
- Laurie Hugo PS
- Nolungile PS
- Redlands PS
- Teske Gedenk PS
- Soetendal Ngk PS
- Hector Peterson SS
- Sunlands PS
- Wellington PS
- Protea HS
- Soyisile PS
- Khanyolwethu SS
2020/21 Financial Year:
- Bellville PS
- Bellville-Noord PS
- Excelsior SS
- Helderkruin PS
- John Ramsay HS
- Labiance PS
- Mseki PS
- Ntwasahlobo PS
- Rhodes Hs.
- Rondebosch Boys' PS
- Rondebosch East PS
- S.A. College Junior School
- Salt River SS
- Siviwe SOS
- Tembaletu LSEN
- Thornton PS
- Vuselela PS
- Zandvliet HS
- Belthorn PS
- Bergvliet PS
- Crystal SS
- Eros LSEN - Roof
- Eros LSEN - Civil and structural
- Fish Hoek PS
- Golden Grove PS
- Good Hope Seminary Junior
- Greenfield Girls' PS
- Groote Schuur HS
- Groote Schuur PS
- Grove PS
- Heathfield HS
- Heathfield HS
- Highlands PS
- Jamaicaweg PS
- Kenwyn PS
- Klipfontein PS
- Liesbeeck PS
- Littlewood PS
- Alpine PS
- Amstelhof PS
- Ashton LS
- Bellville-South SS
- Bergsig PS
- Berzelia PS
- Bongolethu PS
- Bonne Esperance PS
- Bramble Way PS
- Bredasdorp PS
- Breërivier HS
- Carpe Diem Skool
- Charlie Hofmeyr HS
- Clarke Prim
- Dagbreek PS
- Darling LS
- De Rust PS
- De Villiers Graaff PS
- De Villiers Laer.
- De Waalville PS
- Diazville PS
- Dieprivier Vgk PS
- Dirk Boshoff PS
- Dryden Street PS
- Ea Janari PS
- Emil Weder SS
- Franschoek HS
- George SS
- Goeie Hoop PS
- Heidedal PS
- Herbertsdale LS
- Hillside PS
- Hm Beets PS
- Hopefield HS
- Hornlee PS
- Hyde Park PS
- Kairos SS
- Langabuya PS
- Langenhoven Gimnasium
- Lotus SS
- Makupula SS
- Marine PS
- Mcgregor PS
- Mimosa PS
- Montagu Drive PS
- Montagu HS
- Montagu LS
- Montana HS
- Muizenberg HS
- Muizenberg Junior
- Nal'uxolo PS
- Nederburg PS
- Nieuwe Morgen PS
- Niko Brummer PS
- Nomsa Mapongwana PS
- Norwood Central PS
- Nuwe Hoop Lsen
- Ocean View SS
- Okkie Smuts PS
- Paulus Joubert SS
- Pauw Gedenk Prim
- Ravensmead SS
- Riverlands PS
- Rocklands Prim
- Rosendal LS
- Rustasie PS
- Sarepta PS
- Searidge Park PS
- Simon Van Der Stel PS
- Simunye SS
- Sonwabo PS
- St. Michael's PS
- Steenberg Primary
- Steenvliet PS