Health

Question by: 
Hon Rachel Windvogel
Answered by: 
Hon Nomafrench Mbombo
Question Number: 
9
Question Body: 

With regard to pronouncements by the Premier in his SOPA 2022 that the Province is planning five mega health infrastructure projects, including the Belhar, Klipfontein and Helderberg regional hospitals, the Tygerberg Central Hospital development and the Swartland District Hospital:

(a) (i) What are the time frames for these projects and (ii) at what stage are they currently, (b)(i) what is the envisaged total budget for each project and (ii) how much will be budgeted in the new financial year and (c) what plans are in place to guard against delays in the projects?

Answer Body: 

 

WCGH PROJECT NO

PROJECT NAME

COMMIT STATUS

Stage

STRAT BRIEF DATE

PRAC COMP DATE

TOTAL PROJECT COST

2022/23 MTEC 3

2023/24 MTEC 3

 2024/25 MTEC 3

 COMMENT

CI830028

Malmesbury - Swartland Hospital - Replacement

Proposed

Stage 1: Feasability

2022/03/30

2030/06/30

      600 000

          -  

  12 988

  11 802

Awaiting National Health comment and approval and once received will update the brief and issue to WCGTPW as implementing agent. Governance structures with risk mitigation structures will be implemented

CI840025

Belhar - Belhar Regional Hospital - New

Proposed

Stage 1: Feasability

2022/04/30

2032/05/31

   2 900 000

          -  

    1 680

  37 139

Once the details of the accommodation schedule has been completed, a letter will be written to National health to request approval of the revised bed allocation and once approval is received, a brief will be issued to WCGTPW as implementing agent.  Governance structures with risk mitigation structures will be implemented

CI840049

Somerset West - Helderberg Regional Hospital - District Hospital Replacement

Proposed

Still to be initiated

2023/06/30

2034/04/30

   1 400 000

          -  

          -  

          -  

Site issues will be finalised in 2022/23 and detailed bed numbers need to be confirmed in 2022/23 to complete the schedule of accommodation in 2023. A letter will then be written to National health to request approval of the revised bed numbers and strategic brief is planned to be issued to WCGTP in 2023.  timelines. Governance structures with risk mitigation structures will be implemented

CI840055

Manenberg - Klipfontein Regional Hospital - Replacement Ph1

Active Not Contracted

Stage 2: Concept report

2018/12/03

2031/02/28

   2 201 598

    5 510

  31 340

  15 056

WCGTP currently evaluating PSP tenders.Governance structures with risk mitigation structures will be implemented

HCI850002

Parow - Tygerberg Hospital - Replacement (PPP)

Active Not Contracted

Feasability study

2012/04/01

2030/06/30

 10 500 000

    1 000

    1 000

          -  

Revised feasability study to be presented end of Feb 2022. To be approved by WCG including Treasury. Once WCG supported it will be submitted to National Treasury for approval of TA1 and procurement process will start whereby output specifications will be drafted by Transaction advisor. Governance structures with risk mitigation structures will be implemented

Date: 
Friday, February 25, 2022