Human Settlements

Question by: 
Hon Carol Beerwinkel
Answered by: 
Hon Bonginkosi Madikizela
Question Number: 
1
Question Body: 

(1) Which housing projects are currently being rolled out in (a) greater Kraaifontein, (b) Durbanville, (c) Fisantekraal/Klipheuwel (d) Parow and (e) the Bellville area; if not, why not; if so, what are the relevant details;

(2) (a) how many more units are being planned for each project; (b) which projects are built by (i) contractors  and (ii) Peoples Housing Process (PHP) respectively, and (c) what is the completion date of each project?

Answer Body: 

Answer

The responses to [1])and [2] are contained below in two separate tables under headings:   People’s Housing Process and Contractor built projects.

The following projects in Wallacedene (Greater Kraaifontein) are currently being rolled out as People’s Housing Process Projects

Project Name

Number of units planned

Units completed as at July 2014

Completion date

Wallacedene

 

 

 

Sisonke phase 2    

32

14

30/04/2015

Sakhuxolo Project 2

119

40

19/12/2014

Intsika

200

15

31/03/2015

Nomzabalazo Project 4

200

40

31/03/2015

Masiphathisane

585

96

09/10/2014

Wallacedene Project 3

491

5

31/03/2015

The following Contractor built projects are being driven by the City of Cape Town (CoCT)

Project Name

Number of units planned

Units completed as at July 2014

Completion date

Comments

(a) Greater Kraaifontein

 

 

 

 

Scottsdene:  Social Housing   

500

0

April 2015

Construction in progress

Scottsdene:  (BNG) 

550

0

Dec 2014

Construction in progress

Scottsdene:  Community Residential Units (Rentals)

350

0

March 2015

Construction in progress

Scottsdene: Finance Linked Individual Subsidy Programme (FLISP)

(R3501- R15 000)

208

86

31/03/2015

Construction in progress

(b) Durbanville

 

 

 

 

Morningstar Infill: (BNG)

166

0

2016

The project was approved and the CoCT who will in due course be calling for tenders for development proposals.

(c)Fisanterkraal/ Klipheuwel

 

 

 

 

Fisantekraal:  (BNG)

868

0

No date available as yet as there is no construction schedule available

The project was approved and the CoCT will in due course be calling for tenders for development proposals.

 

(d) Parow

 

 

 

 

Elsies River E Junction:   Social Housing Project

400

0

 

Construction was stopped in September 2013 when the developer faced financial cash flow problems.  The developer is actively pursuing resolution of the financial problems.

 

 

(e) Bellville

 

 

 

 

Highbury Phase 3 (Kuilsriver):  (BNG)

372

0

 

2016

 

Project approved and construction of services (roads, water and sewer) is in progress.

 

Date: 
Friday, July 25, 2014