Human Settlements
(1) Which housing projects are currently being rolled out in (a) greater Kraaifontein, (b) Durbanville, (c) Fisantekraal/Klipheuwel (d) Parow and (e) the Bellville area; if not, why not; if so, what are the relevant details;
(2) (a) how many more units are being planned for each project; (b) which projects are built by (i) contractors and (ii) Peoples Housing Process (PHP) respectively, and (c) what is the completion date of each project?
Answer
The responses to [1])and [2] are contained below in two separate tables under headings: People’s Housing Process and Contractor built projects.
The following projects in Wallacedene (Greater Kraaifontein) are currently being rolled out as People’s Housing Process Projects
Project Name |
Number of units planned |
Units completed as at July 2014 |
Completion date |
Wallacedene |
|
|
|
Sisonke phase 2 |
32 |
14 |
30/04/2015 |
Sakhuxolo Project 2 |
119 |
40 |
19/12/2014 |
Intsika |
200 |
15 |
31/03/2015 |
Nomzabalazo Project 4 |
200 |
40 |
31/03/2015 |
Masiphathisane |
585 |
96 |
09/10/2014 |
Wallacedene Project 3 |
491 |
5 |
31/03/2015 |
The following Contractor built projects are being driven by the City of Cape Town (CoCT)
Project Name |
Number of units planned |
Units completed as at July 2014 |
Completion date |
Comments |
(a) Greater Kraaifontein |
|
|
|
|
Scottsdene: Social Housing |
500 |
0 |
April 2015 |
Construction in progress |
Scottsdene: (BNG) |
550 |
0 |
Dec 2014 |
Construction in progress |
Scottsdene: Community Residential Units (Rentals) |
350 |
0 |
March 2015 |
Construction in progress |
Scottsdene: Finance Linked Individual Subsidy Programme (FLISP) (R3501- R15 000) |
208 |
86 |
31/03/2015 |
Construction in progress |
(b) Durbanville |
|
|
|
|
Morningstar Infill: (BNG) |
166 |
0 |
2016 |
The project was approved and the CoCT who will in due course be calling for tenders for development proposals. |
(c)Fisanterkraal/ Klipheuwel |
|
|
|
|
Fisantekraal: (BNG) |
868 |
0 |
No date available as yet as there is no construction schedule available |
The project was approved and the CoCT will in due course be calling for tenders for development proposals.
|
(d) Parow |
|
|
|
|
Elsies River E Junction: Social Housing Project |
400 |
0 |
|
Construction was stopped in September 2013 when the developer faced financial cash flow problems. The developer is actively pursuing resolution of the financial problems.
|
(e) Bellville |
|
|
|
|
Highbury Phase 3 (Kuilsriver): (BNG) |
372 |
0 |
2016 |
Project approved and construction of services (roads, water and sewer) is in progress. |