Question by: 
Hon Pierre Uys
Answered by: 
Hon Debbie Schäfer
Question Number: 
15
Question Body: 
  1. Whether the need for classrooms at Ridge View Primary School in Mossel Bay will be addressed; if not, why not; if so, (a) when and (b) how many classrooms;
  1. whether the toilets, which are in a very bad condition and inadequate, will be replaced or upgraded; if not, why not; if so, (a) when and (b) to what extent;
  1. when the school will be painted and fenced?
Answer Body: 

(1)     There is a procedure to follow when requesting new classrooms. Schools need to submit a reuest via the District. No such request has been made.

(2)-(3)    The school will be attended to under the Emergency program. The following components include:

  • The school will receive a new fence.
  • Remedial work to retaining walls.
  • Remedial work to movement joints on classrooms blocks.
  • Repair and replacement of failed components in ablution facilities.
  • Work shall commence in April 2015 and the planned completion date is July 2015.

 

Date: 
Friday, March 13, 2015