Health

Question by: 
Hon Lorraine Botha
Answered by: 
Hon Nomafrench Mbombo
Question Number: 
8
Question Body: 

Whether the plan to construct or hand over seven community health facilities has been achieved; if not, why not; if so; what are the relevant details?

Answer Body: 

Below is a status update on the seven projects:

 

 

No.

Project Name

Project Description

Tender award Date

Actual Contract Start Date

Contract End Date

Original Practical Completion Date

Actual Practical Completion (PC) Certificate date

Reason for delays

1

Beaufort West- Beaufort West Hill Side- New Clinic

New Clinic

2015/06/18

2015/06/18

2016/03/25

2016/11/18

2017/05/04

Extension of time was granted to the contractor for availability of building materials for the development of alternate building methods and inclement weather.

2

Citrusdal- Citrusdal Clinic- Upgrade and Additions

Upgrade and Additions

2015/10/20

2015/10/20

2016/10/10

2017/01/16

2016/06/10

Extension of time was granted to the contractor for inclement weather and delays in information from PSP team.

3

Cape Town District Six CHC

New Facility

2014/09/28

2014/09/28

 

2016/07/28

 

Slow performance by the Contractor and delays in information to the Main Contractor from the PSPs and TPW. The quality remains good.  PC contractually 4 April 2017 and contractor currently in penalties. PC anticipated 31 August 2017.

4

George Thembalethu CDC - Replacement

CDC Replacement

2016/03/31

2016/03/31

 

2017/11/30

 

No delays reported to date. Project on schedule and PC anticipated on 30 November 2017.

5

Napier - Napier New Clinic

New Clinic

2016/09/19

2016/09/19

 

2017/09/29

 

Project on programme, no delays at present. PC anticipated before contracted PS of 27 September 2017.

6

Prince Alfred Hamlet New Clinic

New Clinic

2016/04/22

2016/04/22

 

2017/09/18

2017/10/04

Slow progress by the Contractor, local community unrest for jobs. Some Contractor 2 weeks behind schedule. PC anticipated 31 Oct 2017.

7

Wolseley New Clinic

New Clinic

2016/04/22

2016/04/22

 

2017/09/18

2017/10/02

Slow progress by the Contractor and local community unrest. Contractor 3 months behind schedule. TPW appointing a clerk of works and mentoring contractor to assist with progress. PC planned 2 October 2017 but anticipated End January 2017)

Date: 
Friday, July 21, 2017