Health
Whether the plan to construct or hand over seven community health facilities has been achieved; if not, why not; if so; what are the relevant details?
Below is a status update on the seven projects:
No. |
Project Name |
Project Description |
Tender award Date |
Actual Contract Start Date |
Contract End Date |
Original Practical Completion Date |
Actual Practical Completion (PC) Certificate date |
Reason for delays |
1 |
Beaufort West- Beaufort West Hill Side- New Clinic |
New Clinic |
2015/06/18 |
2015/06/18 |
2016/03/25 |
2016/11/18 |
2017/05/04 |
Extension of time was granted to the contractor for availability of building materials for the development of alternate building methods and inclement weather. |
2 |
Citrusdal- Citrusdal Clinic- Upgrade and Additions |
Upgrade and Additions |
2015/10/20 |
2015/10/20 |
2016/10/10 |
2017/01/16 |
2016/06/10 |
Extension of time was granted to the contractor for inclement weather and delays in information from PSP team. |
3 |
Cape Town District Six CHC |
New Facility |
2014/09/28 |
2014/09/28 |
|
2016/07/28 |
|
Slow performance by the Contractor and delays in information to the Main Contractor from the PSPs and TPW. The quality remains good. PC contractually 4 April 2017 and contractor currently in penalties. PC anticipated 31 August 2017. |
4 |
George Thembalethu CDC - Replacement |
CDC Replacement |
2016/03/31 |
2016/03/31 |
|
2017/11/30 |
|
No delays reported to date. Project on schedule and PC anticipated on 30 November 2017. |
5 |
Napier - Napier New Clinic |
New Clinic |
2016/09/19 |
2016/09/19 |
|
2017/09/29 |
|
Project on programme, no delays at present. PC anticipated before contracted PS of 27 September 2017. |
6 |
Prince Alfred Hamlet New Clinic |
New Clinic |
2016/04/22 |
2016/04/22 |
|
2017/09/18 |
2017/10/04 |
Slow progress by the Contractor, local community unrest for jobs. Some Contractor 2 weeks behind schedule. PC anticipated 31 Oct 2017. |
7 |
Wolseley New Clinic |
New Clinic |
2016/04/22 |
2016/04/22 |
|
2017/09/18 |
2017/10/02 |
Slow progress by the Contractor and local community unrest. Contractor 3 months behind schedule. TPW appointing a clerk of works and mentoring contractor to assist with progress. PC planned 2 October 2017 but anticipated End January 2017) |