[a] How many projects that his Department has already started (excluding the upgrade of informal settlements) will be completed by 2020, (b) in which areas are these projects located, (c) what is the cost of each project and (d) how many residents will benefit from each project in the current financial year?
(a) Thirty-nine (39) projects are currently under construction will be completed by 2020;
(b), (c)& (d) Details of the projects are contained in Annexure A – see attached.
ANNEXURE A
Project |
Area |
Units |
Project cost estimate |
||
Delft The Hague (1012) |
Cape Town: Delft |
1012 |
182 160 000 |
||
Garden Cities Fisantekraal ph1 (868) |
Cape Town: Fisantekraal |
868 |
156 240 000 |
||
Joe Slovo (2886) |
Cape Town: Joe Slovo |
2886 |
519 480 000 |
||
Boystown (1367) |
Cape Town: Boystown |
1367 |
246 060 000 |
||
Delft 7 (518) |
Cape Town: Delft |
518 |
93 240 000 |
||
|
|||||
Forest Village (4820) (4197 houses) |
Cape Town |
4820 |
744 640 000 |
||
Blue Downs Veterans |
Cape Town: Blue downs |
73 |
13 140 000 |
||
Highbury Park (266) |
Cape Town: Highbury |
266 |
47 880 000 |
||
De Doorns Orchards (109) |
De Doorns |
109 |
19 620 000 |
||
|
|||||
Worcester TransHex (7300) |
Worcester |
7300 |
1 314 000 000 |
||
|
|||||
Paarl Vlakkeland (2542) |
Paarl |
2542 |
457 560 000 |
||
McGregor (500) |
McGregor |
500 |
90 000 000 |
||
Bella Vista (312) |
Ceres: Bella Vista |
312 |
56 160 000 |
||
|
|||||
Bredasdorp (158) |
Bredasdorp |
158 |
28 440 000 |
||
|
|||||
Hawston (489) |
Hawston |
489 |
88 020 000 |
||
Suurbraak (35) |
Suurbraak |
35 |
6 300 000 |
||
Grabouw Rooidakke (1169) |
Grabouw |
1169 |
210 420 000 |
||
Grabouw Hillside (348) |
Grabouw |
348 |
62 640 000 |
||
Riviersonderend (135) UISP |
Riviersonderend |
135 |
24 300 000 |
||
Beaufort West S1 (864) |
Beaufort West |
864 |
155 520 000 |
||
Prince Albert (451) |
Prince Albert |
451 |
81 180 000 |
||
Kwanokuthula (1360) |
Bitou |
1360 |
244 800 000 |
||
Protea Park (76) |
George |
76 |
13 680 000 |
||
George Blanco (165) |
George |
165 |
29 700 000 |
||
Melkhoutfontein (170) |
Stilbaai |
170 |
30 600 000 |
||
Vision (1393) UISP |
Knysna |
1393 |
250 740 000 |
||
Hlalani (273) |
Knysna |
273 |
49 140 000 |
||
Ethembeni (180) |
Knysna |
180 |
32 400 000 |
||
Happy Valley (95) |
Knysna |
95 |
17 100 000 |
||
Hornlee (359) |
Knysna |
359 |
64 620 000 |
||
Herbertsdale (154) IRDP |
Herbertsdale |
154 |
27 720 000 |
||
Sonskyn Vallei/Powertown (152) |
Mossel Bay |
152 |
27 360 000 |
||
Rose Valley (875) |
Oudtshoorn |
875 |
157 500 000 |
||
Velddrif Noordhoek (107) |
Velddrif |
107 |
19 260 000 |
||
Klawer (283) UISP |
Klawer |
283 |
50 940 000 |
||
Diazville (563) |
Saldanha |
563 |
101 340 000 |
||
Paternoster (202) |
Paternoster |
202 |
36 360 000 |
||
Hopefield (62) |
Hopefield |
62 |
11 160 000 |
||
Riebeeck West (235) |
Riebeeck West |
235 |
42 300 000 |
||
|
|
||||
|
|||||
|
|
|
|||
TOTAL |
|
32 926 |
R 5 803 720 000 |
Total value of projects: R5, 803,720,000
A total of 32,926 residents will benefit.