Infrastructure

Question by: 
Hon Matlhodi Maseko
Answered by: 
Hon Tertuis Simmers
Question Number: 
9
Question Body: 
  1. How many housing projects in the Western Cape have been delayed as a result of violence, extortion and intimidation by gangs in the last five years and (b) how many beneficiaries have been affected as a result of delayed housing projects due to extortion in the last five years?
Answer Body: 

9 (a)(b) see table below

No.

Housing Project

Beneficiaries Affected

1.

Forest Village

3254

2.

Ithemba, Eerste River

2400

3.

Blue Downs Military Veterans

256

4.

Malibu Conifers

269

5.

Highbury

388

6.

Delft 3&5

1911

7.

Delft 7

505

8.

Delft Infills

389

9.

Our Pride

218

10.

Delft Landscaping

n/a

11.

Blue Downs Infills

256

12.

Fairylands, Paarl

80

13.

Noordhoek, Bergrivier

59

14.

Kalbaskraal, Swartland

134

15.

De Hoop, Swartland

395

16.

Citrusdal

158

17.

Bardale Phase 5a (275 erven)

275

18.

Macassar (Substation

DP7097)

1869

19.

Morkel’s Cottage, Strand

154

20.

Gugulethu Infill (1004

erven)

114

21.

Athlone Infill Housing

600

22.

Beacon Valley, Mitchells Plain

1809

23.

ACSA Symphony Way, Delft

800

24.

Maroela North, Kraaifontein

1700

25.

Airport Infills Project

Luyolo and Tambo Village Sites

729

 

 

 

 

Date: 
Friday, December 2, 2022