  1. With regard to his statement in January 2023 that seven school were to be built in six months:

    Whether the building of these schools has been completed; if not, why not; if so, what are the relevant details?

Answer Body: 

1.         Roosendal Junior High School, Delft: completed

Saxonsea Junior High School, Atlantis: completed

Rivergate Primary School, Rivergate: completed

Nowers Academy, Hout Bay: completed

Edison High School: completed on at a portion of De Grendel Special School.

 Blueridge Primary School, Wallacedene: in progress, delayed due to disruption by community group.

Lwandle Primary School, Lwandle: in progress, delayed due to contractor under-performance.