Infrastructure
- What are the details of the (i) Transhex Catalytic Housing Project, (ii) Bredasdorp Site F Housing Project, (iii) second phase of the Upgrading of Informal Settlements Programme (UISP) housing project in Thembalethu and (iv) Lutzville Housing Project, (b) how many housing units have been delivered to date, (c) what is the comprehensive expenditure breakdown, including (i) a list of all the service providers to whom contracts were awarded, (ii) how much each service provider received and (iii) what are the details of the items with their unit prices and (d) in cases where delays have been experienced, (i) what were the causes of the delays and (ii) what interventions were implemented to address these delays?
(a)(i)(ii)(iii)(iv)(b)(c)(i)(ii)(iii)(d)(i)(ii) See table below.
Transhex Catalytic Housing Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(a)(i) What are the details | Transhex Housing Project: Worcester: Phase 1: Construction of stormwater canal, channels, internal civil engineering services for 2550 erven Transhex and 2412 BNG houses. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) how many housing units have been delivered to date | Phase 1.1 totalling 190 ABT houses completed and handed over to beneficiaries to date. Further phases, totalling a further 2 222 housing units, will be constructed with conventional building methods during the following financial years, which will complete Phase 1. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(c) what is the comprehensive expenditure breakdown |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) a list of all the service providers to whom contracts were awarded, and (ii) how much each service provider received |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) what are the details of the items with their unit prices | CIVIL SERVICES
TOP STRUCTURES
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(d) in cases where delays have been experienced | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) what were the causes of the delays |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) what interventions were implemented to address these delays? | The top structure contractor appointed a Site Administrator to assist with the planning of the work, guidance with management on site and site operations. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Bredasdorp Site F Housing Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(a)(ii) What are the details | The project was approved for 629 units with a budget of R90 912 246.00. 570 units were delivered against a total expenditure of R81 042 358.10. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) how many housing units have been delivered to date | 570 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(c) what is the comprehensive expenditure breakdown |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) a list of all the service providers to whom contracts were awarded, and (ii) how much each service provider received |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) what are the details of the items with their unit prices |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(d) in cases where delays have been experienced, (i) what were the causes of the delays and (ii) what interventions were implemented to address these delays? | None. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Thembalethu UISP Phase 2 Housing Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(a)(iii) What are the details | Thembalethu UISP Phase 2 consists of the construction of 456 Enhanced Serviced Sites (ESS), including 1:1 waterborne toilets. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) how many housing units have been delivered to date | To date, 380 ESS have been handed over to the municipality to hand over to beneficiaries of the project. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(c) what is the comprehensive expenditure breakdown |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) a list of all the service providers to whom contracts were awarded, and (ii) how much each service provider received |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) what are the details of the items with their unit prices |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(d) in cases where delays have been experienced | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) what were the causes of the delays | The contractors had difficulties with cashflow and site management staff. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) what interventions were implemented to address these delays? | The consulting engineer assisted the contractor with the planning of work and guidance with the management. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Lutzville Housing Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(a)(iv) What are the details | The project consists of 362 serviced sites & 362 units. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) how many housing units have been delivered to date | 361 units (one house could not be constructed as it was used for access road to an existing development, hence only 361 units could be built. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(c) what is the comprehensive expenditure breakdown |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(i) a list of all the service providers to whom contracts were awarded |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) how much each service provider received | Sub-contractors: R 3 542 575.00 + 1 722 120.00 = R 5 264 695.00 ( total excludes salaries paid to site staff, machine operators & labour). | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) what are the details of the items with their unit prices |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(d) in cases where delays have been experienced, (i) what were the causes of the delays and (ii) what interventions were implemented to address these delays? | None. |